Latitude | 32.7735 N |
Longitude | 115.4481 W |
Elevation (m) | -4 |
Site Geology | Deep alluvium |
Vs30 (m/sec) | 265 (measured) |
Site Class | D |
Remarks/Notes | Site information sources |
No. of Spans | 2 |
Plan Shape | Straight. |
Total Length | 208' (63.4m). Bridge spans are each 104' (31.7m) long. |
Width of Deck | 34' (10.4m) |
Construction Date | 1971 |
Instrumentation | 1978. Upgraded 1991. 29 accelerometers on the bridge. 3 accelerometers at a free-field site. |
Superstructure Type | Concrete box girder connected monolithically to the abutments. |
Substructure Type | Reinforced concrete piers. 1 column per pier. |
Foundation Type | Timber piles supporting a square concrete footing under central pier. Abutments are also supported by timber piles. |
Remarks | This bridge was instrumented by CSMIP in 1978 with 26 sensors. The instrumentation was upgraded in 1991 to 32 sensors as part of the interagency agreement between Caltrans and DOC. |